December Update
During December, the capping beam for the retaining wall progressed and is now two-thirds complete. In addition, the sewer trenching on the lower ground floor was installed. Excavation is now underway for the 25m pool. Work has been progressing on the lower plantroom, which has been covered in orange geo-tech fabric for the shutdown period.
The construction site will be shut down over the Christmas break. Work will re-start on 8 January. Dust mitigation measures will continue over the shutdown, with ground sprinklers/mister hoses running every two hours.