10 September 2020
Webinar Information session
04 February 2021
DA Notification - First round opens
25 February 2021
DA Notification - First round closes
01 March 2021
DA Notification - Second round opens
31 March 2021
DA Notification - Second round closes
24 December 2020
DA lodged
17 August 2021
DA Approval by Sydney North Planning Panel
Sydney North Planning Panel are an independent panel assessing Council DA
18 August 2022
Tender opens
27 September 2022
Tender closed.
31 October 2022
Council approves construction tender
18 November 2022
Final day pool hall is open.
19 November 2022
Pool hall is closed.
19 December 2022
Initial construction site fence line installation
21 December 2022
Creche is closed
24 January → 25 January 2023
Access to lower car park closed due to site preparation works
January 2023
Changes to WLC car park and centre entrance and removal of trees to enable redevelopment begins
February 2023
Demolition of the pool hall commences
April 2023
Demolition of pool hall complete
April 2023
Construction of new pool hall underway