Latest Project Update – June 2025
Construction progress on site over last month
· Roofing on Pool Hall - Commencement of Kingspan roofing to southern side
· Structural steel roof framing connecting the new pool hall to the exist. central spine
· Structural steel roof framing over new community room near entrance
· Internal sheeting of eastern feature wall
· Subfloor installation of Air conditioning ducting
· Existing Plant Room – New Concrete topping slab complete
· Window frames – installation of the window frame to the Spa and adjoining areas
Focus of construction work in coming month
· Completion of roofing sheets on southern side of pool hall
· Installation of Luxalon Ceiling
· Platform Lift concrete bases and walls
· Family change room – services installation
· Continuation of the Subfloor installation of the Air conditioning ducting
· Roofing – Existing Central Spine– Commencement of new roof
· Works for new Main Switchboard Room
Completed works
· Since the pool closed on 19 November 2022, the following works have been completed:
· Site establishment
· Demolition of the old pool hall
· Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
· Construction of new piles to support the pool hall
· Structural retaining wall on the site’s north-eastern boundary completed
· Capping of contaminated soil on 100% of the site
· New stormwater line in Small Street
· Below ground backwash tanks for the 25m and program pools
· Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
· Concrete ring beams to support steel columns
· Concrete slabs for upper level plant rooms
· Structural steel columns & roof beams to northern & southern sector of the site
· Steel framed wall on Eastern side
· Installation of new Electrical Substation
· Timber Purlins
· Installation of 2 x Mechanical A/C Units
· Official water testing of all pool shells
· Kingspan sheeting on northern roof of the pool hall
· Roofing & cladding on the existing sports hall
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Sports Hall is now closed for re-roofing works, the Health club remains open until re-roofing works move to the central spine area.
Expected project completion date Feb 2026