Latest Project Update – June 2025

Construction progress on site over last month

· Roofing on Pool Hall - Commencement of Kingspan roofing to southern side

· Structural steel roof framing connecting the new pool hall to the exist. central spine

· Structural steel roof framing over new community room near entrance

· Internal sheeting of eastern feature wall

· Subfloor installation of Air conditioning ducting

· Existing Plant Room – New Concrete topping slab complete

· Window frames – installation of the window frame to the Spa and adjoining areas

Focus of construction work in coming month

· Completion of roofing sheets on southern side of pool hall

· Installation of Luxalon Ceiling

· Platform Lift concrete bases and walls

· Family change room – services installation

· Continuation of the Subfloor installation of the Air conditioning ducting

· Roofing – Existing Central Spine– Commencement of new roof

· Works for new Main Switchboard Room

Completed works

· Since the pool closed on 19 November 2022, the following works have been completed:

· Site establishment

· Demolition of the old pool hall

· Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.

· Construction of new piles to support the pool hall

· Structural retaining wall on the site’s north-eastern boundary completed

· Capping of contaminated soil on 100% of the site

· New stormwater line in Small Street

· Below ground backwash tanks for the 25m and program pools

· Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa

· Concrete ring beams to support steel columns

· Concrete slabs for upper level plant rooms

· Structural steel columns & roof beams to northern & southern sector of the site

· Steel framed wall on Eastern side

· Installation of new Electrical Substation

· Timber Purlins

· Installation of 2 x Mechanical A/C Units

· Official water testing of all pool shells

· Kingspan sheeting on northern roof of the pool hall

· Roofing & cladding on the existing sports hall

Other relevant project updates over the last month

Continuation of the Asbestos Management Plan - daily air monitoring continuing

Sports Hall is now closed for re-roofing works, the Health club remains open until re-roofing works move to the central spine area.

Expected project completion date Feb 2026

Share Latest Project Update – June 2025 on Facebook Share Latest Project Update – June 2025 on Twitter Share Latest Project Update – June 2025 on Linkedin Email Latest Project Update – June 2025 link