Latest Project Update – April 2025

Construction progress on site over last month

  • Roofing – Installation of waterproof membrane and roofing top hats
  • Official Pool Testing – 80% complete
  • Timber Roof Purlins – These will be a feature of the centre and are now all installed
  • Glazing – Circular window frames installed in the eastern wall
  • Demolition – Of the old Spa room floor has commenced
  • Existing Sports Hall & Central Spine – Scaffolding has been erected for recladding works

Focus of construction work in coming month

  • Installation of curved roof sheets on north side of pool hall
  • Installation of Ceiling
  • Completion of demolition works to old spa & area for platform lift
  • Preparation works for new Main Switchboard Room
  • Preparation works for excavation for underground rainwater tanks

Completed works

  • Since the pool closed on 19 November 2022, the following works have been completed:
  • Site establishment
  • Demolition of the old pool hall
  • Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
  • Construction of new piles to support the pool hall
  • Structural retaining wall on the site’s north-eastern boundary completed
  • Capping of contaminated soil on 100% of the site
  • New stormwater line in Small Street
  • Below ground backwash tanks for the 25m and program pools
  • Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
  • Concrete ring beams to support steel columns
  • Concrete slabs for upper level plant rooms
  • Structural steel columns & roof beams to northern & southern sector of the site
  • Steel framed wall on Eastern side
  • Installation of new Electrical Substation
  • Timber Purlins
  • Installation of 2 x Mechanical A/C Units

Other relevant project updates over the last month

Continuation of the Asbestos Management Plan - daily air monitoring continuing

Sports Hall is now closed for re-roofing works, the Health club remains open until re-roofing works move to the central spine area.

Expected project completion date Feb 2026