Latest Project Update – April 2025
Construction progress on site over last month
- Roofing – Installation of waterproof membrane and roofing top hats
- Official Pool Testing – 80% complete
- Timber Roof Purlins – These will be a feature of the centre and are now all installed
- Glazing – Circular window frames installed in the eastern wall
- Demolition – Of the old Spa room floor has commenced
- Existing Sports Hall & Central Spine – Scaffolding has been erected for recladding works
Focus of construction work in coming month
- Installation of curved roof sheets on north side of pool hall
- Installation of Ceiling
- Completion of demolition works to old spa & area for platform lift
- Preparation works for new Main Switchboard Room
- Preparation works for excavation for underground rainwater tanks
Completed works
- Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern & southern sector of the site
- Steel framed wall on Eastern side
- Installation of new Electrical Substation
- Timber Purlins
- Installation of 2 x Mechanical A/C Units
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Sports Hall is now closed for re-roofing works, the Health club remains open until re-roofing works move to the central spine area.
Expected project completion date Feb 2026
Share Latest Project Update – April 2025 on Facebook
Share Latest Project Update – April 2025 on Twitter
Share Latest Project Update – April 2025 on Linkedin
Email Latest Project Update – April 2025 link
