Latest Project Update – August 2025

Construction progress on site over last month

  • Continuation of gutters, flashing & downpipes
  • Completion of small roof connecting Pool Hall to existing building
  • Grinding of pools in preparation for application waterproof coating
  • Ceilings to Pool Hall – 90% Complete
  • Timber panelling to internal eastern wall
  • Family Change Room – completion of services
  • Refit of existing Plant Room with 25m pool filters
  • Main Switchboard installed
  • Upper Car Park – commencement of excavation for rainwater tanks

Focus of construction work in coming month

  • Installation of roof anchors on new pool hall
  • Completion of waterproofing coating to pool shells in preparation for tiling
  • Commencement of tiling to Program Pool
  • Family change room – commencement of wall linings
  • Commence framing for timber ceiling in Spa
  • Upper Car Park – installation of rainwater tanks
  • Existing Central Spine – Internal fitout worksAllied Health room – services install and structural floor works

Completed works

  • Since the pool closed on 19 November 2022, the following works have been completed:
  • Site establishment
  • Demolition of the old pool hall
  • Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
  • Construction of new piles to support the pool hall
  • Structural retaining wall on the site’s north-eastern boundary completed
  • Capping of contaminated soil on 100% of the site
  • New stormwater line in Small Street
  • Below ground backwash tanks for the 25m and program pools
  • Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
  • Concrete ring beams to support steel columns
  • Concrete slabs for upper level plant rooms
  • Structural steel columns & roof beams to northern & southern sector of the site
  • Steel framed wall on Eastern side
  • Installation of new Electrical Substation
  • Timber Purlins
  • Installation of 2 x Mechanical A/C Units
  • Official water testing of all pool shells
  • Kingspan sheeting on northern roof of the pool hall
  • Roofing & cladding on the existing sports hall & central spine
  • Cladding to existing sports hall & central spine
  • Installation of Solar Panels
  • Tower Crane removed
  • Internal scaffolding removed from the Pool Hall

Other relevant project updates over the last month

Continuation of the Asbestos Management Plan - daily air monitoring continuing

The main central spine of the centre is now closed for refubishment works, and the main entry has been relocated to the south/west corner of the sports hall. The Gym will be closed from 30th June 2025, for a number of months while internal works are in progress.

Expected project completion date Feb 2026