Latest Project Update – August 2025
Construction progress on site over last month
- Continuation of gutters, flashing & downpipes
- Completion of small roof connecting Pool Hall to existing building
- Grinding of pools in preparation for application waterproof coating
- Ceilings to Pool Hall – 90% Complete
- Timber panelling to internal eastern wall
- Family Change Room – completion of services
- Refit of existing Plant Room with 25m pool filters
- Main Switchboard installed
- Upper Car Park – commencement of excavation for rainwater tanks
Focus of construction work in coming month
- Installation of roof anchors on new pool hall
- Completion of waterproofing coating to pool shells in preparation for tiling
- Commencement of tiling to Program Pool
- Family change room – commencement of wall linings
- Commence framing for timber ceiling in Spa
- Upper Car Park – installation of rainwater tanks
- Existing Central Spine – Internal fitout worksAllied Health room – services install and structural floor works
Completed works
- Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern & southern sector of the site
- Steel framed wall on Eastern side
- Installation of new Electrical Substation
- Timber Purlins
- Installation of 2 x Mechanical A/C Units
- Official water testing of all pool shells
- Kingspan sheeting on northern roof of the pool hall
- Roofing & cladding on the existing sports hall & central spine
- Cladding to existing sports hall & central spine
- Installation of Solar Panels
- Tower Crane removed
- Internal scaffolding removed from the Pool Hall
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
The main central spine of the centre is now closed for refubishment works, and the main entry has been relocated to the south/west corner of the sports hall. The Gym will be closed from 30th June 2025, for a number of months while internal works are in progress.
Expected project completion date Feb 2026
Share Latest Project Update – August 2025 on Facebook
Share Latest Project Update – August 2025 on Twitter
Share Latest Project Update – August 2025 on Linkedin
Email Latest Project Update – August 2025 link
