Latest Project Update – July 2025

Construction progress on site over last month

  • Roofing on Pool Hall - Continuation of the Kingspan roofing to southern side
  • Grandstand structural steel roof beams complete, commencing installation of purlins
  • Ceilings to Pool Hall – 75% Complete
  • Family Change Room – Services Installation is continuing
  • New Plant Room – 85% complete
  • Glazing – Subheads & sills installed, framing has commenced

Focus of construction work in coming month

  • Completion of all roofing sheeting
  • Completion of Luxalon Ceiling in the pool hall
  • Family change room – Services installation
  • Continuation of the Subfloor installation of the Air conditioning ducting
  • Western Car Park – Will be closed from 4th August 2025 to enable the installation of in-ground rainwater and OSD tanks
  • Installation of new Main Switchboard

Completed works

  • Since the pool closed on 19 November 2022, the following works have been completed:
  • Site establishment
  • Demolition of the old pool hall
  • Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
  • Construction of new piles to support the pool hall
  • Structural retaining wall on the site’s north-eastern boundary completed
  • Capping of contaminated soil on 100% of the site
  • New stormwater line in Small Street
  • Below ground backwash tanks for the 25m and program pools
  • Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
  • Concrete ring beams to support steel columns
  • Concrete slabs for upper level plant rooms
  • Structural steel columns & roof beams to northern & southern sector of the site
  • Steel framed wall on Eastern side
  • Installation of new Electrical Substation
  • Timber Purlins
  • Installation of 2 x Mechanical A/C Units
  • Official water testing of all pool shells
  • Kingspan sheeting on northern roof of the pool hall
  • Roofing & cladding on the existing sports hall

Other relevant project updates over the last month

Continuation of the Asbestos Management Plan - daily air monitoring continuing

The main central spine of the centre is now closed for re-roofing works, and the main entry has been relocated to the south/west corner of the sports hall. The Gym will be closed from 30th June 2025, for a number of months while internal works are in progress.

Expected project completion date Feb 2026