Latest Project Update – July 2025
Construction progress on site over last month
- Roofing on Pool Hall - Continuation of the Kingspan roofing to southern side
- Grandstand structural steel roof beams complete, commencing installation of purlins
- Ceilings to Pool Hall – 75% Complete
- Family Change Room – Services Installation is continuing
- New Plant Room – 85% complete
- Glazing – Subheads & sills installed, framing has commenced
Focus of construction work in coming month
- Completion of all roofing sheeting
- Completion of Luxalon Ceiling in the pool hall
- Family change room – Services installation
- Continuation of the Subfloor installation of the Air conditioning ducting
- Western Car Park – Will be closed from 4th August 2025 to enable the installation of in-ground rainwater and OSD tanks
- Installation of new Main Switchboard
Completed works
- Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern & southern sector of the site
- Steel framed wall on Eastern side
- Installation of new Electrical Substation
- Timber Purlins
- Installation of 2 x Mechanical A/C Units
- Official water testing of all pool shells
- Kingspan sheeting on northern roof of the pool hall
- Roofing & cladding on the existing sports hall
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
The main central spine of the centre is now closed for re-roofing works, and the main entry has been relocated to the south/west corner of the sports hall. The Gym will be closed from 30th June 2025, for a number of months while internal works are in progress.
Expected project completion date Feb 2026