Latest Project Update – May 2025
Construction progress on site over last month
· Roofing – Pool Hall -Installation of Kingspan roofing to northern side
· Roofing – Existing Sports Hall – Roofing installed
· Official Pool Testing of Pool Shells – Complete
· Insulation – Installed in Spa and Eastern walls
· Demolition – Of the old Spa room floor complete
Focus of construction work in coming month
· Installation of curved roof sheets on southern side of pool hall
· Installation of Ceiling
· Works to upgrade area of old plant room
· Works for new Main Switchboard Room
· Preparation works for new roofing over the existing central spine
Completed works
· Since the pool closed on 19 November 2022, the following works have been completed:
· Site establishment
· Demolition of the old pool hall
· Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
· Construction of new piles to support the pool hall
· Structural retaining wall on the site’s north-eastern boundary completed
· Capping of contaminated soil on 100% of the site
· New stormwater line in Small Street
· Below ground backwash tanks for the 25m and program pools
· Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
· Concrete ring beams to support steel columns
· Concrete slabs for upper level plant rooms
· Structural steel columns & roof beams to northern & southern sector of the site
· Steel framed wall on Eastern side
· Installation of new Electrical Substation
· Timber Purlins
· Installation of 2 x Mechanical A/C Units
· Official water testing of all pool shells
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Sports Hall is now closed for re-roofing works, the health club remains open until re-roofing works move to the central spine area