• Latest project update - August 2024

    Share Latest project update - August 2024 on Facebook Share Latest project update - August 2024 on Twitter Share Latest project update - August 2024 on Linkedin Email Latest project update - August 2024 link

    Construction progress on site over last month

    • 25m pool – concrete shell for pool and pool covers complete

    • Program Pool – concrete shell complete

    • Learn to Swim pool – concrete shell complete

    • Subfloor plumbing for the water jets and play features and concrete pour for the Childrens Leisure Pool completed

    • Spa walls concrete shell complete and pool cover base poured

    • Family change room – formwork commenced

    • Formwork for the ring beam to support the pool hall’s structural steel underway

    Focus of construction work in coming month

    • Leisure Pool – pour concrete to base slab & walls on the 3rd September 2024

    • Work will progress with the pool hall concourse concrete slab

    • 25m Pool – concrete pour for ramps

    • Program Pool – pour pool cover Base

    • Spa – pour blanket cover walls

    • Family Change Room – pour floor slab


    Completed works

    Since the pool closed on 19 November 2022, the following works have been completed:  

    • Site establishment

    • Demolition of the old pool hall  

    • Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.

    • Construction of new piles to support the pool hall

    • Structural retaining wall on the site’s north-eastern boundary completed

    • Capping of contaminated soil on 100% of the site

    • New stormwater line in Small Street

    • Below ground backwash tanks for the 25m and program pools

    • Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa

    Other relevant project updates over the last month

    • Continuation of the Asbestos Management Plan - daily air monitoring continuing

    Centre facilities currently open

    • Health club and sports hall, including a full range of land-based group fitness classes


    Image from crane camera, 20 AugustChildren's Leisure pool from work

    Spa




    Construction progress on site over last month

    • 25m pool – concrete shell for pool and pool covers complete

    • Program Pool – concrete shell complete

    • Learn to Swim pool – concrete shell complete

    • Subfloor plumbing for the water jets and play features and concrete pour for the Childrens Leisure Pool completed

    • Spa walls concrete shell complete and pool cover base poured

    • Family change room – formwork commenced

    • Formwork for the ring beam to support the pool hall’s structural steel underway

    Focus of construction work in coming month

    • Leisure Pool – pour concrete to base slab & walls on the 3rd September 2024

    • Work will progress with the pool hall concourse concrete slab

    • 25m Pool – concrete pour for ramps

    • Program Pool – pour pool cover Base

    • Spa – pour blanket cover walls

    • Family Change Room – pour floor slab


    Completed works

    Since the pool closed on 19 November 2022, the following works have been completed:  

    • Site establishment

    • Demolition of the old pool hall  

    • Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.

    • Construction of new piles to support the pool hall

    • Structural retaining wall on the site’s north-eastern boundary completed

    • Capping of contaminated soil on 100% of the site

    • New stormwater line in Small Street

    • Below ground backwash tanks for the 25m and program pools

    • Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa

    Other relevant project updates over the last month

    • Continuation of the Asbestos Management Plan - daily air monitoring continuing

    Centre facilities currently open

    • Health club and sports hall, including a full range of land-based group fitness classes


    Image from crane camera, 20 AugustChildren's Leisure pool from work

    Spa