Latest Project Update – June 2025
Share Latest Project Update – June 2025 on Facebook Share Latest Project Update – June 2025 on Twitter Share Latest Project Update – June 2025 on Linkedin Email Latest Project Update – June 2025 linkConstruction progress on site over last month
· Roofing on Pool Hall - Commencement of Kingspan roofing to southern side
· Structural steel roof framing connecting the new pool hall to the exist. central spine
· Structural steel roof framing over new community room near entrance
· Internal sheeting of eastern feature wall
· Subfloor installation of Air conditioning ducting
· Existing Plant Room – New Concrete topping slab complete
· Window frames – installation of the window frame to the Spa and adjoining areas
Focus of construction work in coming month
· Completion of roofing sheets on southern side of pool hall
· Installation of Luxalon Ceiling
· Platform Lift concrete bases and walls
· Family change room – services installation
· Continuation of the Subfloor installation of the Air conditioning ducting
· Roofing – Existing Central Spine– Commencement of new roof
· Works for new Main Switchboard Room
Completed works
· Since the pool closed on 19 November 2022, the following works have been completed:
· Site establishment
· Demolition of the old pool hall
· Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
· Construction of new piles to support the pool hall
· Structural retaining wall on the site’s north-eastern boundary completed
· Capping of contaminated soil on 100% of the site
· New stormwater line in Small Street
· Below ground backwash tanks for the 25m and program pools
· Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
· Concrete ring beams to support steel columns
· Concrete slabs for upper level plant rooms
· Structural steel columns & roof beams to northern & southern sector of the site
· Steel framed wall on Eastern side
· Installation of new Electrical Substation
· Timber Purlins
· Installation of 2 x Mechanical A/C Units
· Official water testing of all pool shells
· Kingspan sheeting on northern roof of the pool hall
· Roofing & cladding on the existing sports hall
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Sports Hall is now closed for re-roofing works, the Health club remains open until re-roofing works move to the central spine area.
Expected project completion date Feb 2026
-
Latest Project Update – May 2025
Share Latest Project Update – May 2025 on Facebook Share Latest Project Update – May 2025 on Twitter Share Latest Project Update – May 2025 on Linkedin Email Latest Project Update – May 2025 linkConstruction progress on site over last month
· Roofing – Pool Hall -Installation of Kingspan roofing to northern side
· Roofing – Existing Sports Hall – Roofing installed
· Official Pool Testing of Pool Shells – Complete
· Insulation – Installed in Spa and Eastern walls
· Demolition – Of the old Spa room floor complete
Focus of construction work in coming month
· Installation of curved roof sheets on southern side of pool hall
· Installation of Ceiling
· Works to upgrade area of old plant room
· Works for new Main Switchboard Room
· Preparation works for new roofing over the existing central spine
Completed works
· Since the pool closed on 19 November 2022, the following works have been completed:
· Site establishment
· Demolition of the old pool hall
· Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
· Construction of new piles to support the pool hall
· Structural retaining wall on the site’s north-eastern boundary completed
· Capping of contaminated soil on 100% of the site
· New stormwater line in Small Street
· Below ground backwash tanks for the 25m and program pools
· Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
· Concrete ring beams to support steel columns
· Concrete slabs for upper level plant rooms
· Structural steel columns & roof beams to northern & southern sector of the site
· Steel framed wall on Eastern side
· Installation of new Electrical Substation
· Timber Purlins
· Installation of 2 x Mechanical A/C Units
· Official water testing of all pool shells
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Sports Hall is now closed for re-roofing works, the health club remains open until re-roofing works move to the central spine area
-
Update on Sports Hall Closure – Roofing Works
Share Update on Sports Hall Closure – Roofing Works on Facebook Share Update on Sports Hall Closure – Roofing Works on Twitter Share Update on Sports Hall Closure – Roofing Works on Linkedin Email Update on Sports Hall Closure – Roofing Works linkRecent rainfall has caused delays to the roofing replacement works currently underway at the Willoughby Leisure Centre Sports Hall. Originally estimated for completion by the end of May, the works are now expected to be completed by the end of June.
As a result, the Sports Hall will remain closed until the end of June.
During this time:
The Health Club (gym) remains open as usual.
Group fitness classes will continue to run within the facility and at Artarmon Community Hall, 139 Artarmon Road
We understand this delay may cause some inconvenience and appreciate your patience and understanding. We will keep you updated on any further developments as the project progresses.
-
Latest Project Update – April 2025
Share Latest Project Update – April 2025 on Facebook Share Latest Project Update – April 2025 on Twitter Share Latest Project Update – April 2025 on Linkedin Email Latest Project Update – April 2025 linkConstruction progress on site over last month
- Roofing – Installation of waterproof membrane and roofing top hats
- Official Pool Testing – 80% complete
- Timber Roof Purlins – These will be a feature of the centre and are now all installed
- Glazing – Circular window frames installed in the eastern wall
- Demolition – Of the old Spa room floor has commenced
- Existing Sports Hall & Central Spine – Scaffolding has been erected for recladding works
Focus of construction work in coming month
- Installation of curved roof sheets on north side of pool hall
- Installation of Ceiling
- Completion of demolition works to old spa & area for platform lift
- Preparation works for new Main Switchboard Room
- Preparation works for excavation for underground rainwater tanks
Completed works
- Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern & southern sector of the site
- Steel framed wall on Eastern side
- Installation of new Electrical Substation
- Timber Purlins
- Installation of 2 x Mechanical A/C Units
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Sports Hall is now closed for re-roofing works, the Health club remains open until re-roofing works move to the central spine area.
Expected project completion date Feb 2026
-
Project News - April 2025
Share Project News - April 2025 on Facebook Share Project News - April 2025 on Twitter Share Project News - April 2025 on Linkedin Email Project News - April 2025 linkWilloughby City Council is increasing the budget allocation for the Willoughby Leisure Centre project—from the original $38.9 million to $65 million - following a necessary change in project scope. In line with this, we are also announcing a new anticipated opening in February, 2026.
This adjustment responds to challenges encountered due to latent in-ground site conditions.
The video below describes more about the project, the history of the Willoughby Leisure Centre site at Bicentennial Reserve, and the unique challenges our project team has faced due to the site’s prior uses.
We will continue to provide regular updates on the project and timeline through this page and other channels, as new information becomes available.
For more information, see the updated FAQs on the taskbar at the right hand side of this page
-
Latest Project Update – March 2025
Share Latest Project Update – March 2025 on Facebook Share Latest Project Update – March 2025 on Twitter Share Latest Project Update – March 2025 on Linkedin Email Latest Project Update – March 2025 linkConstruction progress on site over last month
- Timber Purlins – Installation of main & intermediate purlins
- Plant room waterproof floor and installation of insulation & Pool Filters
- Installation of Electrical Substation
- Official testing of all pool shells
- Plant room services fit out
- Installation of roof liner
Focus of construction work in coming month
- Installation of roofing on pool hall
- Installation of Ceiling
- Preparation works for new Platform Lift
- Completion of Scaffolding around the existing sports hall & central spine
- Commencement of re-roofing of existing sports hall
Completed works
- Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern & southern sector of the site
- Steel framed wall on Eastern side
- Installation of new Electrical Substation
- Timber Purlins
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open, including the Health club and sports hall. The sports hall will be closed from mid-April 2025 during re-roofing works.
Expected project completion date 2025
-
Latest Project update - February 2025
Share Latest Project update - February 2025 on Facebook Share Latest Project update - February 2025 on Twitter Share Latest Project update - February 2025 on Linkedin Email Latest Project update - February 2025 linkConstruction progress on site over last month
- Timber Purlins – Installation of main & intermediate purlins
- Plant room waterproof floor and installation of insulation & Pool Filters
- Installation of Electrical Substation
- Circular window frames on eastern elevation
Focus of construction work in coming month
- Installation of ceiling and insulation
- Installation of roofing
- Official testing of all pool shells
- Installation of electrical substation
- Plant room services fit out
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern & southern sector of the site
- Steel framed wall on Eastern side
- Installation of new Electrical Substation
- Timber Purlins
Other relevant project updates over the last month
- Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open
- Health club and sports hall, including a full range of land-based group fitness classes
Expected project completion date
- 2025
-
Latest Project Update - January 2025
Share Latest Project Update - January 2025 on Facebook Share Latest Project Update - January 2025 on Twitter Share Latest Project Update - January 2025 on Linkedin Email Latest Project Update - January 2025 linkConstruction progress on site - January 2025
- Structural steel (Columns & curved roof beams) erection on the northern & southern sector of the site
- Surface preparation for floor finishes/tiling on Learn to Swim Pool & Leisure Pool
Focus of construction work in coming month
- Installation of Timber Purlins
- Complete Water testing on all pools & balance tanks
- Installation of electrical substation
- Existing plant room slab integration
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern & southern sector of the site
Other relevant project updates over the last month
- A new time lapse video, showing construction between January and July 2024, has been added to the project website.
- Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open
- Health club and sports hall, including a full range of land-based group fitness classes
Expected project completion date
- 2025
-
Latest Project update - December 2024
Share Latest Project update - December 2024 on Facebook Share Latest Project update - December 2024 on Twitter Share Latest Project update - December 2024 on Linkedin Email Latest Project update - December 2024 linkConstruction progress on site December 2024
• Major structural steel (columns & curved roof beams) erection on northern sector of the site complete
• Additional concourse slab around pools complete
• Hydraulic and electrical enabling works for pool commenced
Focus of construction work in coming month
• Structural steel (Columns & curved roof beams) erection on southern sector of the site
• Delivery to site of electrical substation
• Surface preparation for floor finishes/tiling on Learn to Swim Pool & Leisure Pool
• Existing plant room slab integration
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
• Site establishment
• Demolition of the old pool hall
• Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
• Construction of new piles to support the pool hall
• Structural retaining wall on the site’s north-eastern boundary completed
• Capping of contaminated soil on 100% of the site
• New stormwater line in Small Street
• Below ground backwash tanks for the 25m and program pools
• Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
• Concrete ring beams to support steel columns
• Concrete slabs for upper level plant rooms
• Structural steel columns & roof beams to northern sector of the site
Other relevant project updates over the last month
-
Latest project update - November 2024.
Share Latest project update - November 2024. on Facebook Share Latest project update - November 2024. on Twitter Share Latest project update - November 2024. on Linkedin Email Latest project update - November 2024. linkConstruction progress on site over last month
- Concourse slab around pools complete
- Leakage test passed for Learn to Swim Pool & Program Pool
- Scaffold ‘bird cage’ installed for steel framework construction
- Structural steel (Columns & curved roof beams) erection on northern sector of the site
Focus of construction work in coming month
- Structural steel (Columns & curved roof beams) erection on southern sector of the site
- Delivery to site of electrical substation
- Surface preparation for floor finishes/tiling on Learn to Swim Pool & Leisure Pool
- Existing plant room slab integration
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern sector of the site
Other relevant project updates over the last month
- Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open
- Health club and sports hall, including a full range of land-based group fitness classes
Expected project completion date
- 2025